Construction of 7.2km of 280mm OD PE Rising Main including 13 air valves, 13 odour filters and 13 scour valves. The construction was a combination of Horizontal Directional Drilling and open trenching with depths of 2m – 4.5m.
Construction of 3.2km of 250mm OD PE Water Main including 8 air valves, 6 fire hydrants and 15 sluice valves. The Construction was a combination of Horizontial Directional Drilling and open trenching with depths of 2m – 3.5m.
We carried out all construction including pressure testing and disinfection as per Watercare Standards.
The project value was $4.2 million and was constructed over a 12 month period.